Theoverhead rateusing the traditional (plantwide) approach is 160% and theoverhead ratesusing the activity-based costing approach is $70What is the overhead rate using the a traditional (plantwide) approach?= Estimated overhead / Direct labor cost= $240,000 / (50,000 + 100,000)= $240,000 / 150,000= 160%What is the overhead rates using the activity-based costing approach?Given thatMachininghave 140,000 estimated overhead andMachine setuphave 100,000 estimated overheadPer machine hour= Cost of machining / Number of machine hourPer machine hour =$140,000 / (1,000+1,000)Per machine hour =$140,000 /2, 000Per machine hour =$70Read more aboutoverhead ratebrainly.com/question/26454135...